Bulk Chemical Processing
The client had a non-compliant chemical tank farm that supplied their key central processing area. This had to be decommissioned and removed but only after the new system was installed, commissioned and tested. The new system comprised of a new 29m3 bulk caustic tank in a recently installed tank farm and drawing out bulk Nitric Acid and Sodium Hypochlorite tanks, with a 200m run along a pipe-bridge.
Key Outcomes:
A Sodium Hypochlorite dilution system
An IBC (1,000L) chemical dosing systems for difficult to handle cleaning chemicals
A secure safety shower ring main network for 12 showers in the factory
Chemical tanks installation, all pumps and piping
600m chemical pipework for three chemicals
Value: $3 Million
Duration: 12 Months
Man-hours: 9,000
Project Type: Fixed Price